close

Roadwatch Update

6 min read

Traffic Signal repairs will be done at the following intersections from 9:00 am to 3:00 pm:

2/9/10 – Cape Coral Pkwy & Vincennes

2/10/10 – Cape Coral Pkwy & Nicholas

2/11/10 – Cultural Club & Nicholas

Cape Coral Police Department will be onsite all 3 days to direct traffic

I. Road Projects

Bonita Beach Road – Road Widening Project East of Bonita Grande Drive -The week of

February 2, 2009, construction activities began on the widening of Bonita Beach Road east of

Bonita Grande Drive. Construction activities are expected to last until March 2010. Proposed

work includes the widening of approximately two miles of Bonita Beach Road from two lanes to

four lanes. Work will also include rebuilding portions of the existing two lanes, installation of

drainage and relocation of a force main. Two travel lanes will be maintained in order not to

disrupt the flow of traffic in the area. Call Eyra Cash with any questions at

(239) 533-8562

Buckingham Road Paved Shoulders from SR82 to Neal Road -Work will begin February 8,

2010 to add 4′ wide paved shoulders on Buckingham Rd. This work will require one lane to be

closed during much of the work effort. Lane closures will be limited to off peak hours, after 9

a.m. and before 3 p.m.; however an alternate route is suggested. Work is expected to be

complete by April 1, 2010.

Colonial Blvd (CR 884) Six Laning from I-75 to State Rd 82 (approx. 2.7 miles in length)

Construction activities began on Monday, August 10, 2009. Proposed work consists of widening

an existing four lane highway facility, to a six lane urbanized divided highway. This will include

the installation of street lighting, signalization, bridge widening and utility modifications. Two 8-

foot-wide asphalt multi-use sidewalks along the north and south sides of the road will be added.

The tentative completion date is April, 2011.

Colonial Blvd – Utility work will be ongoing around Treeline Avenue on both the north and

south side of Colonial for the next several weeks for relocation of utilities. Work will be ongoing

under the I-75 Bridges along Colonial. Construction Traffic is heavy, so please drive through the

area with caution. If you have any questions please contact Eyra Cash, Lee County Dept. of

Transportation at (239) 533-8562.

Florence Ave & State Rte 80, Shandler’s Community Park Entrance On February 2, 2010,

construction activities anticipated to take 2 weeks will begin. The proposed work will remove

the SR 80/Florence entrance. Access to the park can be obtained from Royal Palm Park Road.

Please contact Eyra Cash at 533-8562 with any questions or comments.

Gladiolus Drive Widening from Pine Ridge Road to Winkler Road Construction activities

are continuing on Gladiolus Drive and on Bass Road to widen Gladiolus Drive from 2 lanes to 6

lanes from Winker Road to Bass Road and to 4 lanes from Bass Road to Pine Ridge Road and to

widen Bass Road from 2 lanes to 4 lanes from Health Park to Gladiolus Drive. Motorists are

advised that a lane reduction is in place on the westbound approach of Gladiolus Drive to Winker

Road. Construction activities are currently occurring through out the corridor.

Gladiolus -Lane closures may occur and will typically be at night time between 7:00 pm and

6:00 am with some work occurring off the roadway during the day. The tentative completion

date is Fall, 2010. Please contact Robert Phelan at 533-8594 with any questions.

(new 2/4/2010 Gladiolus)

Beginning at 7 p.m., Wednesday, February 3nd and Thursday, February 4th construction

crewwill pave the intersection at Gladiolus Drive and Winkler Road. Law enforcement

will be present to direct traffic during intermittent lane closures. The work is expected to be

complete by 6 a.m.

On Thursday, February 4th and Friday, February 5th from 7 p.m. to 6 a.m. construction

crews anticipate placing the final lift of asphalt on Bass Road south of Gladiolus Drive to

Health Park. Expect intermittent lane closures. The work is expected to be complete by 6

a.m. However, if delayed due to weather or additional work is required; crews will complete

the paving on Sunday, February 7th, between 7 p.m. to 6 a.m. Flagmen will be on site to

direct traffic.

The Contractor is anticipating activation of the signal at A&W Bulb Road and Gladiolus

Drive the week of February 15th, the signal will operate in flash mode prior being placed into

full operation. In the event of delays the activation of the signal may be postponed until the

week of February 22nd.

Lee Blvd/ Sunshine Blvd. -Intersection of Lee Boulevard/Sunshine Boulevard On February

20, 2010, construction activities anticipated to take 5 months to complete will begin. The

proposed work will extend along Sunshine Boulevard approximately 1000′ each direction from

Lee Boulevard; and includes the addition of a left turn lane and traffic signal modifications.

Sanibel Toll Plaza Bicycle/Pedestrian Improvements – Work will begin February 8, 2010 to

add paved shoulders/construct a bike path through the toll booth area. McGregor Blvd. will be

resurfaced through the limits of the work area and additional boat trailer parking will be added

for the boat ramp. All through travel lanes will remain open during day light hours; activities

requiring lane closures (resurfacing) will be done at night. Work is expected to be complete by

April 30, 2010.

Summerlin Rd. from Cypress Lake Dr. to Boyscout Rd. work continues on widening the

southbound roadway from north of College to Cypress Lake, and on the northbound roadway

near Boy Scout Rd. Work on the retaining wall on the south side has been suspended due to the

presence of asbestos and will resume once a determination of the amount and disposable method

has been approved. Work on the retaining wall on the North side of the intersection will begin

the week of Jan. 11th.

The dual left turn lanes on College Pkwy completion date is summer of 2010. Please contact

Sarah Clarke at 533-8718 with any questions.

II. Road/Bridge Maintenance

Del Prado We will be performing bridge maintenance on the bridge north of Coronado on Del

Prado. This will be night work starting Oct. 29th until the end of January, 2010 on Thursday

nights, with lane closures starting at 7:00 pm until 3:30 am. If you have any questions please call

Doug Busbee at 533-9429.

III. Landscaping

Summerlin Road Landscaping Lee County DOT Operations will be managing the

installation of irrigation and landscaping along Summerlin Road, between Sanibel Island and

Gladiolus Drive. This project is scheduled to be completed in late March 2010. Lane closures

and traffic impacts may occur. If you have any questions please contact Bob DeBrock at 239-

533-9425.

IV. County-Wide Road Resurfacing

Resurfacing various streets countywide began May 5, 2009 and will last for 12 months.

V. County-Wide Sidewalk Construction

VI. Signal Work

SR 80 & Ortiz – Beginning 1/19/10 Major Signal repairs to begin at SR 80 & Ortiz. The work is

planned maintenance in conjunction with road work. Expect delays until March 1st.