Roadwatch update from LC DOT

7 min read

ROADWATCH UPDATE

April 22 through April 28, 2010

I. Road Projects

Bonita Beach Road – Road Widening Project East of Bonita Grande Drive -The week of

February 2, 2009, construction activities began on the widening of Bonita Beach Road east of

Bonita Grande Drive. Construction activities are substantially complete. Proposed work

includes the widening of approximately two miles of Bonita Beach Road from two lanes to four

lanes. Work will also include rebuilding portions of the existing two lanes, installation of

drainage and relocation of a force main. Two travel lanes will be maintained in order not to

disrupt the flow of traffic in the area. Call Eyra Cash with any questions at (239) 533-8562.

Buckingham Road Paved Shoulders from SR 82 to Neal Road -Work began on

February 8, 2010 to add 4-foot-wide paved shoulders on Buckingham Rd. This work will

require one lane to be closed during much of the work effort. Lane closures will be limited to off

peak hours, after 9 a.m. and before 3 p.m.; however an alternate route is suggested. Work is

expected to be complete by May 1, 2010. The paved shoulders are complete; the entire road will

be resurfaced in the next few weeks; exact schedule hasn’t been determined. The work will take

2 to 3 days and work will be done at night.

Colonial Blvd (CR 884) Six Laning from I-75 to State Rd 82 (approx. 2.7 miles in length)

Construction activities began on Monday, August 10, 2009. Proposed work consists of widening

an existing four lane highway facility, to a six lane urbanized divided highway. This will include

the installation of street lighting, signalization, bridge widening and utility modifications. Two 8-

foot-wide asphalt multi-use sidewalks along the north and south sides of the road will be added.

The tentative completion date is April, 2011.

Colonial Blvd – Utility work began on Oct 1, 2009 and will be ongoing around the bridge

over Cypress Slough and Treeline Avenue on both the north and south side of Colonial for a

few more weeks for relocation of utilities and final tie-ins. There will be storm drain

installation related activities on the north and south side of the roadway. Bridge construction

related activities will continue for the next few months on the south side of the roadway.

Construction activities will continue under the I-75 Bridges along Colonial. Construction

Traffic is heavy, so please drive through the area with caution. If you have any questions

please contact Eyra Cash, Lee County Dept. of Transportation at (239) 533-8562.

Daniels Parkway / Bell Tower Intersection Improvements

Construction activities began on Monday March 1, 2010 on improvements to Daniels Parkway

between US 41 and the intersection of Brynwood Lane and Big Pine Way. This work will

include improvements to the signal and Sauer Dr/Bell Tower Drive, median improvements, turn

lane extensions and sidewalks on the south side of the roadway.

This work will require lane closures during much of the work effort. Prior to April 5, 2010 lane

closures will be limited to night time hours only, 7pm to 6am. After April 5, 2010 lane closures

may also occur during off peak hours, after 9 a.m. and before 3 p.m.; however an alternate route

is suggested. The tentative completion date is September, 2010. Contact Robert Phelan at 533-

8594 with any questions.

Edison Ave – Work started April 12 on Edison Ave between West 6th st and West 7th St in

Lehigh Acres. East County Water Control District will be replacing a pipe. This project will last

until approx. May 3rd. Any questions please contact Billy Byrd @ 707-6946

Gladiolus Drive Widening from Pine Ridge Road to Winkler Road Construction activities

are continuing on Gladiolus Drive and on Bass Road to widen Gladiolus Drive from 2 lanes to 6

lanes from Winker Road to Bass Road and to 4 lanes from Bass Road to Pine Ridge Road and to

widen Bass Road from 2 lanes to 4 lanes from Health Park to Gladiolus Drive. Motorists are

advised that a lane reduction is in place on the westbound approach of Gladiolus Drive to Winker

Road. Construction activities are currently occurring through out the corridor. Lane closures

may occur and will typically be at night time between 7:00 pm and 6:00 am with some work

occurring off the roadway during the day. The tentative completion date is Summer, 2010

contact Robert Phelan at 533-8594 with any questions.

On Friday, April 9, 2010 the contractor is anticipating shifting eastbound traffic to the new travel

way for the entire project length. Between Pine Ridge Road and Bass Road one lane of traffic

will be open in each direction. Motorists are advised that new traffic patterns will be present

throughout the area including the signalized intersections of Pine Ridge Road, Hagie

Dr/Alexandria Dt, A&W Bulb Road and Bass Road. After traffic is shifted work motorist are

advised that work will be occurring in the median.

Lee Blvd/ Sunshine Blvd. -Intersection of Lee Boulevard/Sunshine Boulevard On February

20, 2010, construction activities began and will take approximately 5 months to complete.. The

proposed work will extend along Sunshine Boulevard approximately 1000′ each direction from

Lee Boulevard; and includes the addition of a left turn lane and traffic signal modifications.

Please contact Eyra Cash at 533-8562 with any questions or comments.

Littleton Rd on April 8, 2010, construction activities began on the south side of Littleton Road

from US 41 to OLD US 41, and is anticipated to take 6 months to complete. Proposed work

includes construction of a 5′ sidewalk. Please contact Eyra Cash at 533-8562 with any questions

or comments.

Sanibel Toll Plaza Bicycle/Pedestrian Improvements – Work began February 8, 2010 to add

paved shoulders/construct a bike path through the toll booth area. McGregor Blvd. will be

resurfaced through the limits of the work area and additional boat trailer parking will be added

for the boat ramp. All through travel lanes will remain open during day light hours; activities

requiring lane closures (resurfacing) will be done at night. Work is expected to be complete by

April 30, 2010.

Summerlin Rd. from Cypress Lake Dr. to Boy Scout Rd. work continues on widening the

southbound roadway from north of College to Cypress Lake, and on the northbound roadway

near Boy Scout Rd. Work on the retaining wall on the south side has been suspended due to the

presence of asbestos and will resume once a determination of the amount and disposable method

has been approved. Work on the retaining wall on the North side of the intersection is underway.

Traffic will be shifted to the new northbound lanes north of Maple Ave. and work in the median

and on the southbound lanes from Maple Ave. to Boy Scout Rd. began the week of February

15th. Completion date is summer of 2010. Please contact Sarah Clarke at 533-8718 with any

questions.

II. Road/Bridge Maintenance

Cape Coral Bridge – Lee County DOT Operations will be managing the overlay project for the

Cape Coral Bridge West Bound Lanes, Bridge # 124044 on College PKWY. The project is

scheduled for 90 days starting Monday April 5th, 2010. There will be lane closures from 6:00

am to 3:00 pm, including weekends.. If you have any questions, please contact Ehab Guirguis at

533-9400.

New 4/21/2010

Gregory Ave East County Water Control District will be closing Gregory Ave between 28th

St SW and 29th ST SW in Lehigh starting on April 27th thru May 4th to replace a pipe.

Moody Road – We will be performing Bridge maintenance on Moody Road in North Ft Myers

between Pondella and Hancock starting 4/26/10. There will be a lane closure. The project should

be completed by 5/6/10.

III. Landscaping

Summerlin Road Landscaping Lee County DOT Operations will be managing the

installation of irrigation and landscaping along Summerlin Road, between Sanibel Island and

Gladiolus Drive. This project is scheduled to be completed in late April, 2010. Lane closures and

traffic impacts may occur. If you have any questions please contact Bob DeBrock at 239-533-

9425.

IV. County-Wide Road Resurfacing

Resurfacing various streets countywide began May 5, 2009 and will last for 12 months.