Roadwatch Update for Oct. 28 through Nov. 3

5 min read

New 10/21/2010

Hancock Bridge Parkway Roadway Improvements – A contractor will be performing

roadway improvements on Hancock Bridge Parkway between Orange Grove Blvd. & SE 24th

Ave. One lane of traffic may be closed between 9:00am and 4:00pm, as conditions dictate. The

work is expected to be completed by November 8, 2010. Contact Michael Tisch at 533-8110

with any questions or comments.

New 10/7/2010

Matlacha Bridge -The replacement of the Matlacha Bridge will begin October 11, 2010.

Installation of construction signing and work to shift traffic to the north will be done in the first

few weeks. Traffic will remain on the existing bridge with reduced lane widths; the sidewalk on

the south side of the bridge will be closed. Two way traffic will be maintained during daylight

hours. The project will take approximately two years. If you have any questions, contact Sarah

Clarke at 239-533-8718.

Matlacha Bridge update – 10/14/10 -This is a Notification that there will be lane closures on the

Matlacha Bridge the Week of October 18, 2010 beginning Monday night through Friday

morning from 9pm to 6am. Please allow for additional travel time as periodic delays may occur.

Six Mile Cypress Parkway Four Laning Daniels Parkway to south of Winkler Road

Construction project to widen the two lane section of Six Mile Cypress to a four lane divided

highway. This work will include the installation of a signalized intersection at Penzance

Boulevard and the addition of a paved path along the west side of the roadway from Heritage

Palms to Daniels Parkway. The tentative completion date is December 2011.

If you have any questions, please contact Cella Molnar & Associates, Inc. at (239) 337-1071

Summerlin Rd. Update 5/27/2010 – from Cypress Lake Dr. to Boy Scout Rd. Work

continues on widening the southbound roadway from north of College to Cypress Lake, and on

the northbound roadway near Boy Scout Rd. Work to remove the asbestos contamination and to

remove and replace the retaining wall on the south side has begun. The beams for the overpass

will be set throughout the month of July and will entail night time closures of the Summerlin/

College intersection from 7:00 pm to 6:00 am. Detour routes will be posted and off duty police

officers will be on site to direct traffic. Dates for intersection closures throughout the month

will be posted on message boards and in Roadwatch. Completion date is late 2010. Please

contact Sarah Clarke at 533-8718 with any questions.

II. Road/Bridge Maintenance

Update 6/17/2010

Alva Bridge #120042, on Broadway Street over Caloosahatchee – Lee County DOT

Operations will be managing the 15 year rehab project for the Alva Bridge. The job is scheduled

to start July 6, 2010 and finish early 2011, weather permitting. There will be single lane closures

from 9:00 am to 4:00 pm. During some night work activity the drawbridge will be closed to

motor vehicle traffic overnight. Variable message boards will be placed to alert drivers to bridge

closures. If you have any questions, please contact Ehab Guirguis at 533-9400.

New 10/28/2010

Big Carlos Bridge #120028, on Bonita Beach Rd. over Big Carlos Pass – Lee County DOT

Operations will be managing the concrete repairs and overlay project for Big Carlos Bridge. The

job is scheduled to start October 25, 2010 and finish early 2011, weather permitting. There will

be single lane closures from 9:00 am to 4:00 pm. Variable message boards will be placed to alert

drivers to bridge closures. If you have any questions, please contact Ehab Guirguis at 533-9400.

New 10/14/2010

Daniels Parkway Eastbound Road Closure at Railroad tracks (Metro Parkway)

Seminole Gulf Railroad will be performing major rehabilitation of the railway crossing on the

eastbound lanes of Daniels Parkway beginning at 9:00am Monday, October 25, 2010. The

eastbound lanes will be closed for approximately 1 week approaching the railroad crossing. The

anticipated completion date is Monday, November 7, 2010. Motorists traveling between I-75 and

US 41 are advised to avoid this area and seek alternative routes during the construction period; as

the road closure will produce traffic congestion and longer than expected travel times. Please

follow posted detour routes if you are unfamiliar with the area. If you have any questions, please

contact Michael Tisch at (239)533-8110.

Update 10/28/2010

Midpoint Memorial Toll Plaza Demolition/Reconstruction-.

On November 4th, there will be intermittent lane closures as crews place temporary striping for a

November 6th traffic shift. On November 6th eastbound lanes will be shifted to the south. One

westbound lane will be closed from November 8th through November 15th and will be reopened on

November 16th. Until the end of January there will be five westbound travel lanes and two eastbound

travel lanes. Crews are dismantling the roof of the central portion of the toll plaza canopy. During

the toll plaza reconstruction, bicyclists must use the new bike path that was constructed north of

(around the back of) the toll plaza.

The temporary emergency access turnaround will be eliminated permanently.

Effective November 8th oversized/wide-load trucks are permitted in the eastbound lanes of the toll

plaza.

For updates on all lanes closures, traffic shifts and construction progress, please visit the project Web

site at www.LeeBridgeConstruction.com. The project is expected to be complete by Spring 2011.

Contact Cella Molnar & Associates, Inc. at 239-337-1071 with any questions.

III. Landscaping

New 8/12/2010

U.S. 41 Landscaping Lee County DOT Operations will be managing the installation of

irrigation and landscaping along U.S. 41 between Jamaica Bay and San Carlos Blvd. This project

is scheduled to be completed by the end of November 2010. Lane closures and traffic impacts

may occur. If you have any questions please contact Bob DeBrock at 239-533-9425.

Bayshore Road Landscaping Lee County DOT Operations will be managing the

installation of irrigation and landscaping along Bayshore Road, between Slater Road and

Pritchett Parkway. This project is scheduled to be completed by the end of November 2010. Lane

closures and traffic impacts may occur. If you have any questions please contact Bob DeBrock at

239-533-9425.

IV. County-Wide Road Resurfacing

Resurfacing continues on various streets countywide.

V. County-Wide Sidewalk Construction

VI. Signal Work

11/03/2010

Del Prado & SE 26th Signal cabinet replacement on 11/3 from 9:00 AM to 3:00PM; Lee

County Sherriff’s office will be directing traffic.

11/10/2010

Del Prado & Cornwallis Signal cabinet replacement on 11/10 from 9:00 am to 3:00 pm. Lee

County Sheriff’s office will be directing traffic.

11/17/2010

Bonita Beach Rd & Lely/Barefoot Beach – Signal cabinet replacement on 11/11 from 9:00 am to

3:00 pm. Lee County Sheriff’s office will be directing traffic.