LDOT Roadwatch update

8 min read

ROADWATCH UPDATE

Dec. 1, 2011 through Dec 7, 2011

NEW LISTINGS AND UPDATES THIS WEEK

New 12/1/2011

12th St. W Lehigh Road closure between Douglas Ave N to Collins Ave. starting 12/6/2011 through 12/9/2011 between the hours of 9am to 3pm. The traffic will be detoured to Douglas Ave N to 13th St, east to Collins Ave N and then south to 12th St W again, completing the detour. Any questions should be directed to Joe Frantz, 707-6946.

Update 12/1/2011

Bonita Beach Road Six-Laning -Old 41 to Lime Street

Lee County continues work to widen existing Bonita Beach Road from four to six lanes from Old 41 to Lime Street. This project, jointly funded by Lee County Department of Transportation and the City of Bonita Springs, completes the six-laning of Bonita Beach Road from Old 41 to I-75 and adds a bike lane and sidewalk in each direction. Bicycle and pedestrian access will shift from the south side of Bonita Beach Road to the north side this week and will remain on the north side over the next several months. Drainage and utility work continues along the project.

Crews will be paving during the overnight/nighttime hours on Sunday, Dec. 4 through Wednesday, Dec. 7 in preparation for this week’s traffic shift to the north. Crews will also be paving at Arroyal Road for the turn lane improvements. This work may require partial turn lane closures (daytime and nighttime) and lane closures (nighttime) from 7 p.m. to 6 a.m., WEATHER PERMITTING.

During the nighttime/overnight hours on Tuesday, December 6 crews will shift westbound Bonita Beach Road lanes to the north and during the nighttime/overnight hours on Wednesday, December 7, shift the eastbound Bonita Beach Road lanes to the north. This shift is necessary for crews to work on the south side of Bonita Beach Road for the next several months.

PLEASE DRIVE WITH CARE and be aware of heavy equipment entering/exiting the roadway.

Page 2 of 5

Bonita Beach Rd cont’d

Underground utility work will be a large part of this project. The decorative street lighting remains along the roadway and median landscaping will be installed. Please use caution when traveling in the work zone. The project is scheduled to be complete in early 2013. The contractor is APAC Southeast, Inc. If you have any questions, please contact Cella Molnar & Associates at 239-337-1071 or Lee County Department of Transportation, Sarah Clarke at 239-533-8718.

Update 12/1/201

Daniels Parkway Six Laning – Chamberlin Parkway to Gateway Boulevard

Lee County is widening Daniels Parkway from four to six lanes from Chamberlin Parkway to Gateway Boulevard. This project includes reconstructing the Daniels Parkway and Chamberlin Parkway intersection to create a four way signalized intersection. PLEASE DRIVE WITH CARE and be aware of heavy equipment entering/exiting the roadway. Crews are working in the Daniels Parkway median between Chamberlin Parkway and Gateway Boulevard and in the turn lanes for the new Boston Red Sox Stadium.

Westbound traffic is shifted toward the median for crews to work on the outside lanes. Turn lanes will be maintained where possible. Through Spring 2012, Chana Court will be closed at Daniels Parkway for crews to install signals and construct the north side of the Chamberlin Parkway intersection. Local traffic will be permitted access to Chana Court from Treeline Avenue.

The majority of the widening along Daniels Parkway will take place within the median along with some minor shoulder widening and turn lane construction occurring along the outside lanes. Landscaping within the median will be installed as part of the project. In addition, this project will mill and resurface Daniels Parkway from Treeline Avenue to Fuel Farm Road. The roadway work is expected to be complete in February 2012. The contractor is Better Roads, Inc. If you have any questions please contact Cella Molnar and Associates at 239-337-1071 or Lee County Department of Transportation, Rob Phelan, P.E. at 239-533-8594.

Road & Bridge Projects

Update 8/31/2011

Cape Coral Toll Plaza Demolition/Reconstruction

Demolition and reconstruction at the toll plaza continues. The four westbound lanes are shifted to the south (lanes 1 through 4 are shifted to lanes 5 through 8).

Page 3 of 5

Effective immediately, “oversized load” trucks are NOT permitted through the travel lanes of Cape Coral Toll plaza (in either direction). This includes oversized load trucks with State permits. Oversized load truckers should use the Midpoint or north bridges for access to Fort Myers while the toll plaza is under construction. For updates on all lanes closures, traffic shifts and construction progress, please visit the project web site at www.LeeBridgeConstruction.com. The project is expected to be complete by spring, 2012. Contact Cella Molnar & Associates, Inc.

at 239-337-1071,or Randy Cerchie at 239-533-8573 with any questions.

Update 11/17/2011

Colonial Blvd (CR 884) Six Laning from I-75 to State Road 82 (approximately 2.7 miles in length)

Construction activities began on Monday, August 10, 2009. Proposed work consists of widening an existing four-lane highway facility, to a six-lane urbanized divided highway. This will include the installation of street lighting, signalization, bridge widening and utility modifications. Two 8-foot wide asphalt multi-use sidewalks along the north and south sides of the road will be added. The tentative completion date is December, 2011. If you have any questions, they should be directed to Randy Cerchie, 239-533-8573.

Update 11/24/2011

Matlacha Bridge

The replacement of the Matlacha Bridge began October 11, 2010. Traffic will remain on the existing bridge with reduced lane widths; the sidewalk on the south side of the bridge will be closed. Two-way traffic will be maintained during daylight hours. The project will take approximately two years. Additional information is available on the project website at matlachabridge.info. If you have any questions, contact Sarah Clarke at 239-533-8718.

The Matlacha Bridge will periodically be reduced to one lane of traffic. Motorists should expect delays. Flagmen will be on site to direct traffic. PLEASE DRIVE WITH CARE and be aware of workers and equipment on the roadway.

Update 10/13/2011

Six Mile Cypress Parkway Four Laning Daniels Parkway to south of Winkler Road

Motorists should expect traffic shifts throughout the project. PLEASE DRIVE WITH CARE and be aware of heavy equipment entering/exiting the roadway. This project will widen the two-lane section of Six Mile Cypress to a four-lane divided highway. This work will include the installation of a signalized intersection at Penzance Boulevard and the addition of a paved path along the west side of the roadway from Heritage Palms to Daniels Parkway. The tentative completion date is December 2011. If you have any questions, please contact Cella Molnar & Associates, Inc. at (239) 337-1071.

Page 4 of 5

II. Road/Bridge Maintenance

New 10/26/2011

Big Hickory Pass #120026 and Little Carlos Pass # 120055, on Bonita Beach Road – Lee County DOT Operations will be managing the concrete repairs and overlay project for the Big Hickory and Little Carlos Bridges. The job is scheduled to start November 7th, 2011 and finish early 2012, weather permitting. There will be single lane closures from7:00 am to 3:00 pm. Variable message boards will be placed to alert drivers to bridge closures. If you have any questions, please contact Ehab Guirguis at 533-9400.

New 10/26/2011

New Pass #120022, on Bonita Beach Road – Lee County DOT Operations will be managing the concrete repairs and overlay project for the New Pass Bridge. The job is scheduled to start November 7th, 2011 and finish early 2012, weather permitting. There will be single lane closures from7:00 a.m. to 3:00 p.m. Variable message boards will be placed to alert drivers to bridge closures. If you have any questions, please contact Ehab Guirguis at 533-9400.

11/23/2011

Veterans Memorial Parkway & Country Club

Installation of underground conduits will begin on Monday November 28th three hundred feet east of Country Club on the north side of Veterans Memorial Parkway. Crews will be progressing towards the north east corner of Veterans and Country Club. The completion date is scheduled for Thursday December 1. Westbound motorists shall use caution as men and equipment will be located near the travel lanes. Please contact Doug Conley at 281-9137 or Mike Say at 707-7693 with any questions.

III. Landscaping

US 41 Landscaping Lee County DOT Operations will be managing the installation of irrigation and landscaping along US 41, between Littleton Road and the Charlotte County Line. This project is scheduled to be completed by the end of December, 2011. Lane closures and traffic impacts may occur. If you have any questions please contact Bob DeBrock at 239-533-9425.

9/22/11

Plantation Extension Landscaping-Lee County DOT Operations will be managing the installation of irrigation and landscaping along Plantation Extension between Idlewild and Colonial Blvd. This project is scheduled to be completed by the end of February 2012. Lane closures and traffic impacts may occur. If you have any questions, please contact Bob DeBrock at 239-533-9425.

Page 5 of 5

New 11/17/2011

Three Oaks Parkway Landscaping Lee County DOT Operations will be managing the installation of irrigation and landscaping along Three Oaks Parkway, between Corkscrew Road and Alico Road. This project is scheduled to be completed by the end of March, 2012. Lane closures and traffic impacts may occur. If you have any questions, please contact Bob DeBrock at 239-533-9425.

IV. County-Wide Sidewalk Construction

V. Signal Work